Cracks, leaks, uneven floors, poor finishes or work that does not match the plans. A building defect report sets out each defect, why it is a defect and what it will cost to fix, so you can deal with your builder, Fair Trading or the Tribunal from a position of strength.
Most building disputes start with an owner who knows something is wrong but cannot prove it. Builders will often dismiss a complaint, but they take a professional report seriously. A clear list of defects, each with photos, the standard or plan it fails and a cost to fix, changes the conversation.
In NSW, residential building work comes with statutory warranties under the Home Building Act 1989: six years for major defects and two years for other defects. Time limits apply, so it is worth getting defects properly documented early, while the builder is still around and the warranty period is still running.
A defect report is also the starting point for every next step: asking the builder to fix the work, a Fair Trading complaint, an NCAT application or an insurance claim. If the matter goes further, we can turn the same inspection into an NCAT expert report and Scott Schedule without starting again.

If any of these sound familiar, it is worth a call. We will tell you which report or quotation will help, and confirm a fixed fee before we start.
Cracking in walls, ceilings, slabs or render that appeared after construction or a renovation.
Leaking showers, balconies, windows or roofs, or damp and mould in new work.
Sizes, levels, materials or finishes that differ from the approved plans or contract.
Uneven tiling, sloping floors, sticking doors, poor paint or cabinetry problems.
You want an independent check before handing over the last payment.
The builder says the work is fine, or that problems are your fault.
Approaching the end of a warranty period? Get the defects documented now. Call us to talk through your timing.
Plain-language reports you can hand to your builder, Fair Trading, your lawyer or the Tribunal.
Every defect numbered, located and photographed, so nothing gets missed or argued about later.
The National Construction Code, Australian Standard, plan or contract term each item fails to meet.
Whether each item is likely to be a major defect or another defect, which affects the warranty period.
Why the defect happened, so the fix deals with the cause and not just the symptom.
What needs to be done to fix each defect properly.
An itemised cost for each item, so you know what is at stake and can judge any offer.
One inspection, a clear written report, and a path to NCAT if you need it.
Tell us what the report is for and send the contract, plans, photos, correspondence and any Tribunal directions. We confirm the scope, timing and a fixed fee in writing before we attend.
We inspect, measure and photograph every item, take moisture readings and carry out non-destructive checks where they help. Each item is numbered and located.
Each item is assessed against the contract, the approved plans, the National Construction Code, Australian Standards and the manufacturer's instructions, and we identify the cause, not just the symptom.
You receive a written report with our opinion and reasons for each item, the scope of work to fix it and an itemised, fixed-price costing that shows how every figure was calculated.
We answer questions, prepare supplementary reports if new information comes to light, and attend an expert conclave, joint report or hearing when directed, with those fees agreed in advance.
A professional, itemised defect report is often enough to get defects fixed without a hearing. If it is not, it is the foundation of your case.
We build and rectify homes and apartments across Sydney, so we know a real defect when we see one, and what it takes to fix it.
We have built and repaired buildings in Sydney for over 40 years, so our scopes are buildable and our costs come from what the work really takes.
Builder licence 384697C and DBP General Unrestricted registration BUP4254812, including Class 2 apartment buildings.
Reports follow the structure NCAT and the courts expect: instructions, facts and assumptions, reasons for each opinion and the code of conduct acknowledgement.
You know the cost of the inspection and report before we attend. No hourly meter running in the background.
Every item is scoped and priced separately, with preliminaries, access, waste, supervision, margin and GST shown, so the numbers stand up to scrutiny.
Dated photos, measurements, readings and references to the relevant standards for every item, laid out so a member or judge can follow it.
Real reviews from METCON clients.
I called three builders and METCON were the only ones who actually came to look at the site before quoting. Honest pricing, no surprises.
We got three quotes. METCON was not the cheapest but was clearly the most thorough. Worth every dollar.
My partner and I own an original 1920s semi-detached home in Vaucluse, with complex sandstone foundations and multiple structural challenges caused by previous defective works. After years of delays, failed consultants, and no progress, I met Constatine and his team. From the beginning, I was impressed by the detailed review of our plans and the identification of numerous discrepancies that previous builders had missed. The team supported us through lengthy council negotiations, neighbour consultations, and COVID-related delays, even before contracts were signed. Once construction commenced, Constatine and the Meteora Constructions team were exceptional. Progress remained on schedule despite heavy rain, unforeseen structural issues, and highly complex underpinning works that previous builders had refused to undertake. They completed the work efficiently and at significantly less cost than other builders had quoted. I cannot speak highly enough of Constatine and METCON Remedial Services. It is no understatement to say that engaging Constatine and his team saved not only our project, but probably our marriage as well.
Straight answers. Anything else, just ask.
Under the Home Building Act 1989, the statutory warranties last six years for major defects and two years for other defects from completion. Time limits can be complex, so get legal advice early and get the defects documented as soon as you notice them.
A pre-purchase inspection gives a general view of a property before you buy. A defect report looks in detail at specific building work, explains why each item is a defect and costs the fix, ready for a dispute.
Yes. If the dispute goes to the Tribunal, we can prepare the report, or a follow-up report, to meet NCAT's expert evidence requirements.
It depends on the size of the property, the number of items and what the report is for. We confirm a fixed fee in writing before we attend, based on your documents and a short call, so there are no surprises.
Yes. When we act as an expert, our duty is to the Tribunal or court, not to the person who engaged us, and we say so in the report. We disclose any relationship with the parties and whether we have been asked to quote for the rectification work, as the expert code of conduct requires.
Most disputes need more than one document: a defect report, a costing, a Scott Schedule and sometimes a hearing. We can prepare them all from one inspection.
Back to Inspections & ReportsPlain-language guides from our team on the questions we are asked most.
New homes, renovations, extensions, townhouses and apartments across Sydney and surrounding NSW.
Send photos, your contract and plans if you have them. We will tell you what an inspection will cover and the fixed fee.