When a builder goes insolvent, disappears, dies or has their licence suspended, or the contract is terminated, you need to know what it will cost to finish the job and fix what was done wrong. We inspect the half-finished work and prepare a fixed-price, itemised cost to complete and rectify.
For most residential building work over $20,000 in NSW, the builder must have home building compensation cover through the Home Building Compensation Fund. If the builder dies, disappears, becomes insolvent or has their licence suspended for not complying with a money order, the homeowner can claim for incomplete and defective work, up to the policy limits.
A claim needs evidence of what work is incomplete, what is defective and what it will cost to finish and fix. The same is true when an owner terminates a contract and claims the extra cost of completion from the builder at NCAT. A quote that only says "finish the house" is not enough. Each stage and each defect needs its own scope and price.
We inspect the work as it stands, record what has been done and what has not, identify defects in the completed work and prepare a fixed-price, itemised cost to complete and rectify. If you want us to finish the build, the same price applies, so there are no surprises later.

If any of these sound familiar, it is worth a call. We will tell you which report or quotation will help, and confirm a fixed fee before we start.
The builder has gone into liquidation or administration and work has stopped.
The builder has stopped answering and work has not resumed.
The contract has been terminated and you need the cost of finishing the work.
The insurer has asked for a quote to complete or rectify the work.
Some of the completed work is defective and needs fixing before the build can continue.
You want a builder to take over a part-finished job at a known price.
Has your build stopped? Secure the site, take dated photos of everything, and call us. We will tell you what to do next.
Set out so the insurer, the Tribunal or a new builder can see exactly what is left, what is wrong and what it costs.
A record of what is complete, what is partly complete and what has not started, with dated photos.
Defects in the work already done, with the standard or plan each one fails to meet.
A fixed price for each remaining stage and trade, based on the contract scope and plans.
A separate fixed price for each defect, so completion and rectification are not mixed up.
Making the site safe, weatherproof and secure while the claim is assessed.
If you want us to finish the job, the same itemised price becomes our contract price.
We move quickly when a build stops, because exposed work deteriorates and claims have time limits.
Tell us what the report is for and send the contract, plans, photos, correspondence and any Tribunal directions. We confirm the scope, timing and a fixed fee in writing before we attend.
We inspect, measure and photograph every item, take moisture readings and carry out non-destructive checks where they help. Each item is numbered and located.
Each item is assessed against the contract, the approved plans, the National Construction Code, Australian Standards and the manufacturer's instructions, and we identify the cause, not just the symptom.
You receive a written report with our opinion and reasons for each item, the scope of work to fix it and an itemised, fixed-price costing that shows how every figure was calculated.
We answer questions, prepare supplementary reports if new information comes to light, and attend an expert conclave, joint report or hearing when directed, with those fees agreed in advance.
An itemised cost to complete and rectify supports your claim, helps you judge any offer and gives you a builder ready to finish the job.
We take over part-finished homes, extensions and renovations and fix defective work across Sydney.
We have built and repaired buildings in Sydney for over 40 years, so our scopes are buildable and our costs come from what the work really takes.
Builder licence 384697C and DBP General Unrestricted registration BUP4254812, including Class 2 apartment buildings.
Reports follow the structure NCAT and the courts expect: instructions, facts and assumptions, reasons for each opinion and the code of conduct acknowledgement.
You know the cost of the inspection and report before we attend. No hourly meter running in the background.
Every item is scoped and priced separately, with preliminaries, access, waste, supervision, margin and GST shown, so the numbers stand up to scrutiny.
Dated photos, measurements, readings and references to the relevant standards for every item, laid out so a member or judge can follow it.
Real reviews from METCON clients.
We got three quotes. METCON was not the cheapest but was clearly the most thorough. Worth every dollar.
They handled the DA, the engineer, and the build. We didn't have to chase council once. Massive wall, done in under two weeks.
I called three builders and METCON were the only ones who actually came to look at the site before quoting. Honest pricing, no surprises.
Straight answers. Anything else, just ask.
The NSW scheme that protects homeowners when a builder dies, disappears, becomes insolvent or has their licence suspended for not complying with a money order. It covers incomplete and defective work, up to the policy limits.
The insurer assesses the claim and may arrange its own assessment, but owners are often asked for evidence of what is incomplete and defective and what it will cost. An itemised quote from a licensed builder helps.
Yes. We take over part-finished homes, extensions and renovations. The itemised cost to complete becomes the basis of our contract.
It depends on the size of the property, the number of items and what the report is for. We confirm a fixed fee in writing before we attend, based on your documents and a short call, so there are no surprises.
Tell us your deadline when you first call. We schedule inspections around Tribunal and court timetables and agree a delivery date upfront. Urgent matters are often possible, but more notice always gives a better report.
Most disputes need more than one document: a defect report, a costing, a Scott Schedule and sometimes a hearing. We can prepare them all from one inspection.
Back to Inspections & ReportsPlain-language guides from our team on the questions we are asked most.
Houses, extensions, renovations and townhouses across Sydney and surrounding NSW.
Send your contract, plans, progress payments made and photos of the site. We will tell you what is needed and the fee.