Few things are more stressful than a builder who stops turning up halfway through a job. Before you hire someone else to finish it, there are steps that protect your rights and any insurance claim.
Step 1: Secure the site
- Check the site is safe and weather-tight. Open roofs and walls let water in fast.
- Photograph and video the whole site, dated, room by room.
- Note what materials are on site and who owns them.
- Make urgent make safe work only, and keep records of it.

Step 2: Find out why
Is the builder sick, in a payment dispute, out of money, or gone? Search ASIC records for insolvency notices and check the licence on the NSW Government register. The answer decides your path.
Step 3: Follow the contract
Most contracts set out how to give notice of a substantial breach and how to terminate if it is not fixed. Getting this wrong can let the builder claim you terminated wrongly. Get legal advice before you terminate.
Step 4: Get a cost to complete
You need to know what it will cost to finish the work and fix any defects in what was built. A cost to complete report separates three things:
- Work done properly.
- Work done defectively, and the cost to fix it.
- Work not done, and the cost to complete it.
That figure, compared with what is left unpaid under the contract, is usually what you claim.
Step 5: HBCF, if the builder is insolvent or gone
Home building compensation (HBCF) cover can respond if the builder has become insolvent, died, disappeared, or had their licence suspended for failing to comply with a money order. Simply walking off a job is not usually enough on its own. If HBCF applies, you will need a cost to complete and defect evidence. See HBCF claims and cost to complete.
Step 6: NCAT, if the builder is still around
If the builder is still trading, your claim is usually against them, through Fair Trading and then NCAT. See builder refuses to fix defects.
Step 7: Finishing the job
A builder taking over partly built work has to check what is there before building on it. Expect that, and expect the price to reflect it. A fixed price from a builder who has inspected properly avoids surprises.
Cost to complete reports and quotes
We prepare cost to complete and HBCF quotes and can take over and finish the work. The fee is fixed and agreed in writing before the inspection, so you know the cost of the report before you commit. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee in writing before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Can I just get another builder in?
Not until the contract position is clear and the site is documented. Hiring someone else too early can hurt a claim against the original builder or an insurer.
Who owns the materials on site?
It depends on the contract and whether they were paid for. Do not let anyone remove materials until the position is clear.
Is a cost to complete the same as a quote to finish?
Not quite. A cost to complete report also separates defective work and records the state of the site, so it can support a claim. A fixed-price quote to finish can be part of it.