An NCAT decision in a home building dispute can feel final, especially if it went against you on items you were sure about. There is an appeal process, but it is narrow and time-limited. Here is what owners and builders should know.
Internal appeals
Many decisions of NCAT's Consumer and Commercial Division can be appealed to NCAT's Appeal Panel. Appeals on a question of law are generally available. Appeals on other grounds, such as the facts or the merits, usually need leave, and leave is granted only in limited circumstances.
Act quickly
Time limits for lodging an appeal are short, commonly 28 days from the decision or the reasons. Get legal advice as soon as you receive the decision. Ask for written reasons if they were not given.
Appeals are not a rerun
An appeal is not a chance to present the case again with better evidence. New evidence is usually only allowed in narrow circumstances. This is why the expert evidence at the first hearing matters so much.
Common issues raised
- The Tribunal did not deal with an item or an argument.
- No reasons, or inadequate reasons, were given for a finding.
- A legal test was applied wrongly, such as the major defect test.
- Procedural unfairness.
If the other side does not comply
If a builder does not comply with a work order, owners can usually return to the Tribunal. A work order can sometimes be changed to a money order. A fixed-price rectification quote is the evidence needed for that. See work order vs money order.
Avoiding the need to appeal
- Get a full, honest expert report early.
- Cost every item, so the Tribunal can allow items one by one.
- Follow every direction and deadline.
- Prepare the Scott Schedule carefully.
Evidence that holds up
We prepare NCAT expert reports and fixed-price rectification quotes for hearings and for applications after a work order fails. The fee is fixed and agreed in writing before the inspection, so you know the cost of the report before you commit. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee in writing before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Can I appeal because I disagree with the expert?
Disagreeing with findings of fact usually needs leave, which is limited. Get legal advice on your specific grounds.
Does an appeal stop the orders?
Not automatically. A stay may need to be sought. Ask your lawyer.
What if the builder's repair work under a work order is poor?
Document it with photos and an independent report, and seek further orders from the Tribunal.