When NCAT finds building work is defective, it can make a work order or a money order. Knowing which one you want, and why, shapes the evidence you need.
The preferred outcome
Section 48MA of the Home Building Act 1989 says that in deciding a claim about defective work, the Tribunal must have regard to the principle that rectification by the party responsible is the preferred outcome. In practice, unless there is a good reason not to, NCAT will generally order the builder to fix the work.

Work orders vs money orders
| Work order | Money order | |
|---|---|---|
| What happens | The builder returns and fixes the listed defects | The builder pays the cost of having someone else fix them |
| When it suits | The builder is competent, licensed and the relationship is workable | Trust has broken down, the builder is unlicensed or has already failed to fix the work |
| Evidence needed | A clear scope of works | A clear scope and a reliable cost of rectification |
Good reasons for a money order
- The builder has already tried and failed to fix the defects.
- The builder no longer holds a licence for the work.
- The relationship has broken down so badly that a return to site is not workable.
- The builder has shown they do not understand what is wrong.
Your lawyer can advise what applies to you. Either way, you will need evidence.
Proving the cost
A money order is only as good as the cost evidence. The Tribunal needs a scope and cost for each item, showing how the figures were calculated. NCAT's expert evidence rules require this for claims over $30,000. See builder's quotes for NCAT.
Even with a work order, get the scope right
A work order needs to say exactly what has to be done. A vague order leads to more disputes. A detailed scope of works for each defect makes the order clear and enforceable.
If the builder does not comply
If a builder does not comply with a work order, you can go back to the Tribunal. If the builder does not pay a money order, enforcement options apply, and in some cases the Home Building Compensation Fund may be relevant. See HBCF claims.
Rectification quotes in Sydney
We prepare scopes and fixed-price, itemised rectification quotes for work orders and money orders. See rectification quotes. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Can I refuse to let my builder back on site?
You can ask for a money order, but the Tribunal starts from the preferred outcome of rectification by the builder. You need good reasons and evidence.
What is the maximum NCAT can award?
For home building claims, generally up to $500,000. Larger claims go to the courts.
Who fixes the work after a money order?
You choose a licensed builder. The rectification quote used as evidence is often from the builder who then does the work.