When NCAT decides a building dispute, it has to work out what it will cost to fix the defective or incomplete work. That figure usually comes from a builder's quote or an expert's costing. A weak quote can cost you thousands, even when you win on the defects.
Why the quote matters so much
Under section 48MA of the Home Building Act 1989, the Tribunal's preferred outcome is for the party responsible for defective work to fix it, through a work order. But where that is not appropriate, for example because trust has broken down or the builder is no longer licensed, the Tribunal can make a money order. The amount depends on the evidence of cost.
See work order vs money order.

Why lump sum quotes fail
- The Tribunal cannot allow some items and reject others if there is only one figure.
- The other side's expert will say it is inflated, and there is nothing to show it is not.
- It often leaves out access, scaffolding, protection, waste or supervision.
- It may not match the items in the expert report or Scott Schedule.
What a quote should include
| Part | Why it matters |
|---|---|
| Scope for each defect | Shows what is being fixed and how |
| Price for each item | Lets the Tribunal allow items one by one |
| Preliminaries | Site setup, scaffolding, protection, waste and supervision are real costs |
| Margin and GST | Shown separately so they are not mistaken for padding |
| Assumptions and exclusions | What the price depends on, such as engineering or approvals |
| Inspection details | When the site was inspected and by whom |
Inspect before pricing
A quote prepared from photos alone is easy to attack. The builder should inspect the site, measure the work and see the defects in person. Defects often go further than they look, especially leaks and cracking.
Why rectification costs more
Fixing work costs more than doing it right the first time. Defective work has to be removed and disposed of, finished areas protected, the site set up again and trades brought back for small amounts of work. A fair quote reflects this, and the Tribunal generally accepts that a rectifying builder will charge market rates.
Fixed price vs estimate
An estimate is a guess. A fixed-price quote is what a builder will actually do the work for. Where you can, get a fixed-price, itemised quote from a licensed builder who would genuinely do the work. See fixed price vs estimate.
Builder's quotes for NCAT in Sydney
We prepare fixed-price, itemised rectification quotes for NCAT, court and insurance matters, numbered to match your expert report. See rectification quotes. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
How many quotes do I need for NCAT?
There is no fixed rule. One detailed, itemised quote from a licensed builder who inspected the site is usually more useful than several vague ones.
Can the builder who quotes also be my expert?
It is possible, but the expert must disclose any interest, including being asked to do the work. Many people use an expert for the report and a builder's quote for cost.
Is GST included in an NCAT money order?
Usually the cost of rectification includes GST for owners who cannot claim it back, but this depends on your circumstances. Ask your lawyer.