Strata managers sit in the middle of every remedial project: between owners, the committee, engineers, builders and insurers. A clear process saves time, keeps owners informed and protects the manager and the owners corporation.
Stage 1: the first report
- Log the issue with photos, dates and the units affected.
- Decide whether it is urgent: active leaks into units, falling concrete or loose balustrades need make-safe work first.
- Check whether the building is new enough for warranty claims before anyone repairs anything.
- Notify the insurer if the damage may be covered. See strata insurance and leaks.

Stage 2: investigation
For anything beyond a simple repair, engage a remedial engineer or consultant to inspect and report. For Class 2 buildings, the engineer will usually also prepare regulated designs under the DBP Act.
Stage 3: scope and tender
The engineer's report becomes a scope of works. Tender it to suitably licensed and registered remedial builders. Our guide to the tender process explains how to compare prices fairly.
Stage 4: owner approval and funding
- Present the report, photos and tender comparison to the committee.
- Decide whether to fund from the capital works fund or a special levy.
- Call a general meeting if owner approval is needed.
Stage 5: contract and pre-start
- Use a proper building contract, with a defects liability period and retention.
- Check the builder's licence, insurance, home building compensation cover where required, and DBP registration.
- Agree notices to residents, access, work hours and the programme.
Stage 6: during the works
- Hold regular site meetings with the builder and engineer.
- Approve variations in writing only, with the engineer's input.
- Keep residents informed. See living in your building during remedial works.
Stage 7: handover and records
Collect the engineer's sign-off, compliance declarations, flood test results, waterproofing certificates, warranties and photos. Store them with the building records. Diarise the end of the defects liability period and inspect before it ends.
A builder who makes it easier
We work with strata managers on balcony, waterproofing, concrete cancer and facade projects, with clear reporting, resident notices and complete handover documents. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 work. Call 0415 840 500 or book a free inspection.
Frequently asked questions
Who should strata managers call first for a remedial problem?
For anything beyond a simple repair, a remedial engineer or building consultant, who can investigate the cause and specify the repair.
What documents should we keep after remedial works?
Engineer sign-offs, DBP compliance declarations where required, flood test results, waterproofing certificates, warranties and photos.
Should we repair defects in a new building straight away?
Make the area safe, but document defects and get advice on warranty claims before anyone carries out the full repair.