The Design and Building Practitioners Act 2020 (DBP Act) changed how work on NSW apartment buildings is designed, built and documented. Many owners corporations first meet it when they try to fix a leaking balcony or concrete cancer, and find the process has more steps than they expected.
Which buildings it covers
The DBP Act has applied to Class 2 buildings (apartment buildings) since 1 July 2021, and has since been extended to some other building classes. It covers building work on existing buildings as well as new ones.

Building elements
The key concept is a "building element". These include:
- Waterproofing: balconies, podiums, roofs, wet areas, planters and basements.
- Load-bearing components: slabs, beams, columns and structural walls.
- The building enclosure: façades, windows, doors and roofs that keep weather out.
- Fire safety systems.
- Some building services required for compliance.
Remedial work on any of these in a Class 2 building can trigger the DBP Act requirements.
What has to happen
1. Regulated designs
Designs for the building element, such as a waterproofing detail or a concrete repair specification, must be prepared by a registered design practitioner, usually a remedial engineer or consultant.
2. Design compliance declarations
The design practitioner declares the design complies with the Building Code of Australia.
3. Lodgement before work starts
The regulated designs and declarations are lodged on the NSW Planning Portal before work on that building element begins.
4. A registered building practitioner
The builder carrying out the work must be a registered building practitioner. See DBP registered builders explained.
5. Variations
If the design changes during the job, which is common in remedial work once tiles or render come off, the varied design is documented and declared too.
6. Building compliance declaration
At the end, the builder declares the work was built to the regulated designs, and lodges it with the supporting documents.
Why remedial jobs need planning time
In remedial work you often do not know the full scope until things are opened up. A good engineer allows for this with options and rates in the specification. A good builder photographs and documents every hold point so variations can be declared quickly.
What strata committees should ask
- Is the builder a registered building practitioner?
- Who is the design practitioner, and are the regulated designs ready to lodge?
- How will variations be handled and documented?
- What records will we receive at the end?
The duty of care
The DBP Act also created a statutory duty of care owed by those who carry out construction work to current and future owners. See time limits to claim against a builder.
DBP-compliant remedial work
We are DBP registered (BUP4254812) and work with your engineer on regulated designs, hold points, variations and declarations for balcony, waterproofing, façade, concrete and structural repairs. See our strata remedial service or call 0415 840 500.
Frequently asked questions
Does the DBP Act apply to remedial work?
Yes. Building work on building elements such as waterproofing, structure, the enclosure and fire safety systems in Class 2 buildings is covered, including repairs to existing buildings.
Who prepares regulated designs for strata repairs?
A registered design practitioner, usually a remedial engineer or building consultant engaged by the owners corporation.
What is a building compliance declaration?
A declaration by the registered building practitioner that the work was built to the regulated designs, lodged with supporting documents.