When a new apartment building is handed over, owners are usually focused on moving in. But the first two years are when many defects show up, and when important time limits start running. Acting early can save owners a lot of money.
This is general information from a builder, not legal advice. Your strata manager or lawyer can advise on your scheme.
Key time frames in NSW
- Statutory warranties: under the Home Building Act, generally 6 years for major defects and 2 years for other defects, from completion.
- Strata building bond: for buildings covered by the scheme, a bond of 2 percent of the contract price is held, with interim and final inspections in the first two years. See the strata building bond scheme.
- Defects liability period: set by the building contract. See defects liability periods.

What to do first
- Get the documents: plans, warranties, certificates and the building manual from the developer.
- Set up a defect register: one list, with photos, dates and locations.
- Ask owners to report early: leaks, cracks, doors, drainage and anything unusual.
- Get an independent inspection: before the bond inspections, and well before deadlines.
- Notify in writing: report defects to the builder and developer formally.
Common defects in new buildings
- Waterproofing in balconies, bathrooms, podiums and planters. See waterproofing defects.
- Facade sealants and windows. See window leaks.
- Fire safety items. See fire stopping.
- Basement and lift pit water. See lift pits.
- Cracking in render, slabs and walls.
If the builder does not fix defects
Options can include the bond process, NSW Fair Trading or Building Commission NSW, and legal claims. See rectification orders and claim time limits.
Fixing defects properly
Sometimes the original builder rectifies defects, and sometimes another builder is engaged. Either way, the repair should be scoped properly, documented and, for Class 2 buildings, comply with the DBP Act where it applies.
How early action helps
Catching defects early means smaller repairs, a better chance of the builder or bond paying, and protection for the building's reputation and values.
Independent defect inspections and repairs
We inspect newer apartment buildings and rectify defects. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 work. Call 0415 840 500 or book a free inspection.
Frequently asked questions
What should a new strata scheme do about defects?
Get the building documents, keep a defect register, get an independent inspection and notify defects in writing well before time limits.
How long are statutory warranties in NSW?
Generally 6 years for major defects and 2 years for other defects from completion, under the Home Building Act. Get legal advice for your situation.
What is the strata building bond?
A bond of 2 percent of the contract price, lodged by the developer for buildings covered by the scheme, which can be used to fix defects found in the inspections.