A hold point is a stage in the work where the builder stops until the engineer or superintendent has inspected and released it. In remedial work, most of what matters ends up hidden: under render, under tiles, under concrete. Hold points are the only time that work can be checked.
Typical hold points
Concrete repairs
- After break-out, before steel is treated: has the concrete been cut back far enough, and how bad is the steel?
- After steel cleaning or replacement, before reinstatement: is the steel clean, primed and lapped as designed?
- After reinstatement, before coating: is the repair sound and finished correctly?
Waterproofing
- Substrate preparation, before the primer.
- Upstands, outlets, door sills and penetrations, before the membrane.
- After the membrane, before it is covered: thickness, laps and a flood or other test.
Structural work
- Propping in place before removal.
- Steel, fixings and bearings before they are built in or covered.

Records that should come out of it
- Photos of every repair at every hold point, with a location reference.
- Marked-up drawings showing where repairs were done and their size.
- Test results, such as flood tests.
- Product batch records and data sheets.
- Signed release notes from the inspector.
Why it matters
Hold-point records support the building compliance declaration under the DBP Act. They are the evidence if a warranty claim arises. They also justify measured quantities when concrete repairs are paid on rates, which keeps the final account transparent.
Make them practical
Hold points should be booked with enough notice and inspected quickly, or they slow the job. Many engineers accept photo submissions for routine items and visit for the critical ones. Agree the list and the notice period before work starts.
Read concrete cancer quotes compared, balcony flood testing and practical completion and handover. See our concrete cancer repair page.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Who sets the hold points?
Usually the engineer or consultant in the specification, sometimes added to by the superintendent.
Can photos replace site visits?
For routine items, often yes. Critical structural stages are usually inspected in person.
Should the owners corporation keep the records?
Yes. Keep them with the strata records for future buyers, insurers and maintenance.