Remedial works on existing buildings almost always find surprises. The concrete is worse than expected, the steel is in a different place, the outlet cannot go where the drawing shows. On a Class 2 building, those surprises cannot simply be solved on site by the builder.
Why the design matters
Under the Design and Building Practitioners Act, regulated building work must be built in accordance with regulated designs, which are prepared and declared by registered design practitioners. At the end, the registered building practitioner declares that the work was built to those designs. If the work changes, the design has to change too.
What a variation looks like
Generally, where building work will vary from the regulated design, a varied design is prepared by a registered design practitioner, with a design compliance declaration, before the varied work is carried out. Variations are also recorded through the NSW Planning Portal. Confirm the exact steps with your engineer, because the requirements are detailed.
Common reasons designs change
- Concrete damage deeper or wider than allowed for.
- Reinforcement missing, undersized or too corroded to treat.
- Hidden structure that does not match the original drawings.
- Drainage levels that do not allow the designed falls.
- New products substituted because the specified one is unavailable.
How to avoid long delays
- Investigate before design. Opening up sample areas reduces surprises. See trial repairs.
- Design for the likely range. Engineers can include standard details for deeper repairs, so many changes are covered.
- Keep the designer engaged. Make sure the engineer's fee covers site visits and variations during the works.
- Agree a fast process. Photos, a short site meeting and a marked-up detail can turn a variation around quickly.
- Record everything. Hold-point photos show what was found and why the design changed. See hold-point inspections.
Who pays for the change
That depends on the contract. A changed design because of genuinely hidden conditions is usually a variation to the owners corporation. Read strata remedial variations and provisional sums and our Class 2 builder page.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
General information only. Confirm current requirements with your certifier, engineer, strata manager or lawyer.
Frequently asked questions
Can the builder decide on a small change?
Not if it changes regulated work. The design practitioner needs to vary the design.
Does every variation stop work?
Not always. Good planning and standard details let many changes be handled quickly.
Who lodges the varied design?
It is prepared and declared by the design practitioner and recorded through the Planning Portal. Your engineer will confirm the process.