Variations happen on almost every remedial project, because you cannot see everything until the work is opened up. Handled well, they are expected and controlled. Handled badly, they blow the budget and the committee's trust.
Why remedial works have variations
- More concrete cancer than the engineer could see.
- Rotten substrate under tiles and screeds.
- Hidden services in the way.
- Previous poor repairs that have to come out.
- Owner requests for extra work.
Provisional sums
A provisional sum is an allowance in the contract for work that cannot be priced accurately yet. When the work is done, the actual cost replaces the allowance, plus any agreed margin. The contract should say how provisional sums are adjusted.
A good variation process
- The builder identifies the issue and stops that part of the work if needed.
- Photos and a description go to the engineer and strata manager.
- The builder prices the variation, using contract rates where they apply.
- The variation is approved in writing before the work proceeds, except for genuine emergencies.
- A variation register tracks every approved and pending item.
Delegated approvals
Waiting for a committee meeting for every variation stalls the job. Many owners corporations delegate approval of variations up to a set amount to the strata manager or a small group, within the approved budget and contingency. Check what your by-laws and resolutions allow.
Keeping owners informed
| Report | Frequency |
|---|---|
| Variation register | Every progress claim |
| Budget vs actual | Monthly |
| Contingency remaining | Monthly |
| Photos of variations | With each variation |
See progress reports and contingency.
Remedial works without surprises
We photograph and price every variation before proceeding, using contract rates where they apply. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book a free inspection.
Frequently asked questions
Should variations always be approved before work?
Yes, except for genuine emergencies such as making a dangerous area safe. Those should be documented and approved as soon as possible.
What is the difference between a provisional sum and a prime cost item?
A provisional sum covers work and materials that cannot be priced yet. A prime cost item is an allowance for supplying an item, like a fitting, that has not been selected.
Can the builder charge margin on variations?
Usually yes, at the rate set in the contract.