A permanent wall may be safe when the basement slab is complete but unstable halfway through the dig. Temporary works cover that gap.
Examples
- Shoring and trench support.
- Props across an excavation.
- Temporary anchors and piles.
- Crane and piling platforms.
- Supported access ramps.
- Facade or wall bracing.
Design the stages
The designer needs levels and loads at each stage. Include parked machines, material stacks, groundwater and nearby footings. A drawing of the final basement alone is not enough.
Make hold points useful
Before digging to the next level, confirm the previous support is installed and accepted. Name who checks it and who can give permission. Put this on the daily plan.
Watch for change
Cracks, bulging, new water, vibration or unexpected soil should stop work for review. Keep movement records in a form people can understand, with agreed action levels.
Loading errors
An excavator close to an edge can overload a cut even when it is not digging. Spoil, steel and concrete trucks also count. Mark exclusion lines clearly.
Removing support
Props and anchors come out only when the permanent structure can carry the load, in the designer's order. A slab being poured does not always mean it has reached the required strength.
Useful guides: boundary excavation, soldier piles and excavation and footings.
Call 0415 840 500 or request a quote. METCON is a licensed NSW builder (384697C).
Frequently asked questions
Who designs temporary works?
A competent person or engineer suited to the risk and contract.
Can props be moved?
Not without approval from the person responsible for the design.
Is a battered slope temporary works?
It is a temporary control that still needs to suit soil, height and water.