Bulk excavation removes a large volume to create a basement, building platform or car park. A small error in levels can mean paying to remove soil and then paying to bring fill back.
Confirm the final shape
Include slab thickness, footing depth, drainage, working space and temporary slopes. The architectural floor level is not the bottom of the excavation.
Understand volume
Soil expands after digging. A quote measured in the ground and a quote measured in trucks cannot be compared without agreeing how they convert.
Classify what is leaving
Soil may need testing before a facility can accept it. Old fill, demolition waste or stains can change the disposal route and the cost. Keep clean and suspect material separate.
Find rock and water early
Boreholes show selected points, not every metre. Set a rate and measurement method for rock, and say who handles groundwater and rain.
Plan the street
- Truck size and turning.
- Queueing and footpath safety.
- Permitted hours.
- Dust, mud and sediment.
- Trees, wires and nearby schools.
Keep the cut stable
Shoring or safe batters need to progress with the dig. Removing one more bucket to meet a truck schedule can leave a face unsupported.
Ask for a useful quote
It should show volume, disposal assumption, rock, testing, dewatering, shoring and final trim. See rock excavation, temporary works and excavation services.
Call 0415 840 500 or request a quote. METCON is a licensed NSW builder (384697C).
Frequently asked questions
What is bulk excavation?
It is large-volume removal of soil or rock before detailed footing and service excavation.
Who pays if soil is contaminated?
It depends on the contract and information supplied. Agree the process before starting.
Can excavation continue in rain?
Sometimes, if the cut, access, water and sediment remain controlled.