Dig down a metre or two in much of Sydney and you hit sandstone. Basements, pools, retaining walls, footings and driveways often need rock excavation. Done well, it is controlled and predictable. Done badly, it cracks neighbours' houses and blows out the program.
Methods
| Method | How it works | Pros and cons |
|---|---|---|
| Rock breaking | Hydraulic hammer on an excavator | Fast, but noisy and vibration-heavy |
| Rock sawing | Saw cuts the rock face or grid before removal | Clean faces, much less vibration |
| Ripping | Excavator tyne rips weaker or layered rock | Quick in suitable rock |
| Rock grinding | Rotary grinder on an excavator | Precise, lower vibration |
Most sites use a combination: saw the boundaries and faces, then break or rip the core.

Protecting neighbours
- A dilapidation report on neighbouring buildings before starting. See dilapidation reports.
- Vibration monitoring, often a condition of consent near other buildings.
- Saw-cutting along boundaries to separate the excavation from neighbouring rock.
- Geotechnical advice on rock quality, joints and support.
- Working hours and respite periods for noisy work.
Rock faces and support
Sandstone has joints and weaker bands. Exposed faces may need rock bolts, shotcrete or dental concrete, as the geotechnical engineer directs. See slope stabilisation.
Spoil and disposal
Excavated material must be classified before it leaves the site. Clean natural sandstone and soil is often classified as virgin excavated natural material (VENM), which can be reused or disposed of more easily than contaminated fill. Testing and paperwork are part of the job.
Groundwater
Water often runs along sandstone layers. Basements and cuttings may need drainage or waterproofing. See groundwater seepage.
Rock excavation in Sydney
We carry out rock excavation for basements, pools, footings and retaining walls. See excavation and excavation and footings. METCON is a licensed NSW builder (384697C) delivering civil works, excavation and retaining walls across Sydney. Call 0415 840 500 or request a quote.
Frequently asked questions
Will rock breaking crack my neighbour's house?
It can if uncontrolled. Saw-cutting, vibration monitoring and a dilapidation report reduce the risk and protect both sides.
How deep is the rock on my site?
A geotechnical investigation with boreholes tells you before you price the job.
Can excavated sandstone be reused?
Often, for walls or landscaping, if it is sound. Otherwise it is classified and taken away.