When another builder leaves, owners need to know what exists and what risk remains. A quote based only on the visible finish is usually a guess.
Secure the site and records
Keep current plans, approvals, engineer notes, invoices, material warranties and photos. Make unsafe openings and services secure, but preserve evidence if there is a dispute.
Inspect without closing more work
A replacement builder may need structural, waterproofing and service openings. Compare the work with approved plans and record what is incomplete, defective or not yet verifiable.
Split the scope
- Essential make safe and weather protection.
- Rectification of defects.
- Remaining original work.
- New owner variations.
This helps owners and lenders see why a completion price is not the original balance minus invoices.
Confirm approvals and inspections
Do not assume the previous builder's approvals cover changed work. Certifiers, engineers and warranty providers may require a fresh review before work is closed.
Price unknowns honestly
Agree rates or provisional sums for hidden structure, services and rock. Show exclusions. A fixed low number with no investigation can be the dearest choice later.
Restart in a controlled order
Structure and weather first, then services and waterproofing, then finishes. The old programme may no longer match the house.
See cost to complete quotes, builder walked off job and defect rectification.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can a new builder sign off old work?
They can report and price, but cannot simply certify work they did not supervise.
Should the old builder be told?
Get legal advice on notice, access and evidence before changing the contract.
Can we move in between stages?
Only if the responsible approvals, safety and services allow it.