It is one of the most common frustrations for strata committees. The engineer's report gave an estimate, owners budgeted for it, and then the tenders came in higher. Understanding why helps committees set realistic budgets and avoid a second levy.
Why the numbers differ
- Timing: estimates are often months or years old by the time of tender.
- Access: scaffold, swing stages, hoarding and protection are easy to underestimate.
- Preliminaries: site management, amenities, insurance and supervision on an occupied building.
- Quantities: concrete repair areas grow once drummy concrete is sounded and broken out.
- Making good: removing and reinstating tiles, balustrades, screens and finishes.
- Program: working hours limits and staging around residents take longer.
- Risk: builders price unknowns that the specification leaves open.
How to narrow the gap
- Investigate more before tender. Testing and opening up turns guesses into quantities. See concrete testing.
- Get builder input early. A remedial builder can review access and buildability before the specification is final.
- Use a schedule of rates for variable items, so they are priced fairly. See lump sum vs schedule of rates.
- Include a contingency in the budget. See contingency budgets.
- Compare tenders like for like, item by item. See the tender process.
Do not just take the cheapest
A tender well below the others may have left things out. Ask each tenderer to confirm their scope, inclusions and exclusions. Variations later can cost more than the difference.
Telling owners
Explain the reasons at the information session and in the meeting papers. Owners accept a higher figure when they understand it. See owners information sessions.
Realistic pricing
We price remedial works with full allowances for access, staging and making good, and explain every line. See strata remedial works. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book an inspection.
Frequently asked questions
Should we re-tender if prices are high?
Only if the scope or market has changed. Re-tendering the same scope often brings similar prices and delays the work.
Can the scope be reduced to fit the budget?
Sometimes, by staging. Removing essential items usually costs more later.
Why do builders include exclusions?
To be clear about what is not priced. Read them carefully when comparing tenders.