Remedial work is different from new building. You often cannot see how much concrete cancer or water damage there is until you open things up. How the contract is priced decides who carries that uncertainty.
The main pricing models
| Model | How it works | Best for |
|---|---|---|
| Lump sum | One fixed price for a defined scope | Well-defined work, such as re-waterproofing known balconies |
| Schedule of rates | Agreed rates per unit (per square metre, per lineal metre, per item), paid on measured quantities | Concrete repairs and render patching where quantities are unknown |
| Lump sum plus rates | Fixed price for known items, rates for the unknowns | Most strata remedial projects |
| Provisional sums | An allowance for work that cannot yet be priced | Items that depend on what is found |

Why schedule of rates suits concrete repairs
An engineer can estimate how much concrete cancer there is, but the true quantity is only known once drummy areas are sounded and broken out. Paying agreed rates for measured repairs is fairer than a builder guessing high in a lump sum.
Controlling a schedule of rates
- Quantities are measured and recorded jointly before repair.
- Photos of every repair location, before and after.
- The engineer or superintendent signs off quantities.
- Regular reporting against the budget.
Standard contracts
Larger remedial projects often use Australian Standard contracts, such as AS 4000, with special conditions for remedial work. Residential building work must also meet Home Building Act contract requirements. Your engineer, project manager or lawyer can advise.
Comparing tenders
When builders tender on rates, compare the total using the same estimated quantities for every tender. A low rate on a small item does not matter much. A high rate on the biggest item does. See the tender process.
Variations and provisional sums
See variations and provisional sums.
Remedial pricing that committees can follow
We price strata remedial work in the format your engineer specifies, with clear rates and measured records. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book a free inspection.
Frequently asked questions
Is a lump sum safer for the owners corporation?
Only when the scope is well defined. Where quantities are unknown, a lump sum often includes a large risk allowance you pay whether it is needed or not.
Who measures the quantities?
Usually the builder measures and the engineer or superintendent checks, with photos for every location.
Can we mix pricing methods?
Yes. Most remedial contracts combine lump sum items with rates and provisional sums.