Strata Remedial Contracts: Lump Sum vs Schedule of Rates

18 November 2026 · 4 min read · By the METCON team

Remedial work is different from new building. You often cannot see how much concrete cancer or water damage there is until you open things up. How the contract is priced decides who carries that uncertainty.

The main pricing models

ModelHow it worksBest for
Lump sumOne fixed price for a defined scopeWell-defined work, such as re-waterproofing known balconies
Schedule of ratesAgreed rates per unit (per square metre, per lineal metre, per item), paid on measured quantitiesConcrete repairs and render patching where quantities are unknown
Lump sum plus ratesFixed price for known items, rates for the unknownsMost strata remedial projects
Provisional sumsAn allowance for work that cannot yet be pricedItems that depend on what is found
Concrete repair quantities are only known once drummy areas are broken out.
Concrete repair quantities are only known once drummy areas are broken out.

Why schedule of rates suits concrete repairs

An engineer can estimate how much concrete cancer there is, but the true quantity is only known once drummy areas are sounded and broken out. Paying agreed rates for measured repairs is fairer than a builder guessing high in a lump sum.

Controlling a schedule of rates

  • Quantities are measured and recorded jointly before repair.
  • Photos of every repair location, before and after.
  • The engineer or superintendent signs off quantities.
  • Regular reporting against the budget.

Standard contracts

Larger remedial projects often use Australian Standard contracts, such as AS 4000, with special conditions for remedial work. Residential building work must also meet Home Building Act contract requirements. Your engineer, project manager or lawyer can advise.

Comparing tenders

When builders tender on rates, compare the total using the same estimated quantities for every tender. A low rate on a small item does not matter much. A high rate on the biggest item does. See the tender process.

Variations and provisional sums

See variations and provisional sums.

Remedial pricing that committees can follow

We price strata remedial work in the format your engineer specifies, with clear rates and measured records. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book a free inspection.

Frequently asked questions

Is a lump sum safer for the owners corporation?

Only when the scope is well defined. Where quantities are unknown, a lump sum often includes a large risk allowance you pay whether it is needed or not.

Who measures the quantities?

Usually the builder measures and the engineer or superintendent checks, with photos for every location.

Can we mix pricing methods?

Yes. Most remedial contracts combine lump sum items with rates and provisional sums.

Written by the METCON teamMeteora Constructions Pty Ltd. Licensed NSW builder 384697C, DBP registered BUP4254812, 40+ years building across Sydney.
Related services

How we can help.

Everything in this article is work we do every week across Sydney.

Strata Remedial Works
Keep reading

More articles.

Practical guides from a licensed Sydney builder.

All articles

Got a project in mind?

Book a free site assessment. Straight answers on cost, scope and timeline.

Call now Free Quote