A large balance may be too small if a facade is failing. A small balance may be manageable if the building is newer and the next major work is many years away. Look at future work, not the dollar total on its own.
Build the forecast from the building
- List roofs, facades, balconies, lifts, car parks and services.
- Record age, condition and confidence.
- Add investigation before large unknowns.
- Include scaffold, design, approvals and contingency.
- Place each item in a likely year.
- Compare with planned contributions.
Replace old forecasts with actual reports and tender prices when they arrive.
Costs people leave out
- Access and street protection.
- Temporary services and parking.
- Engineering and contract administration.
- Asbestos or hidden concrete damage.
- Resident reinstatement.
- Cost increases between report and construction.
Show the gap clearly
For every major year, record opening fund, contributions, work, closing fund and possible shortfall. A single ten-year average can hide the year when money runs out.
Choose between paths
Owners may increase regular levies, stage work, raise a special levy, borrow or use a combination. Finance does not make an urgent defect safe while the decision is delayed.
Keep three categories
Must do, planned renewal and optional improvement should have separate totals. It prevents a new lobby consuming money meant for a leaking roof.
Review after every report
A facade investigation, roof repair or failed tender should update the next forecast, not sit in a separate folder.
See capital works plans, prioritising repairs and special levies.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
General information only. Confirm current requirements with your certifier, accredited practitioner or lawyer.
Frequently asked questions
Is there a percentage rule?
A general percentage can mislead. Condition, size, timing and planned work are more useful.
Can emergency money be held separately?
Use and classification depend on scheme rules and approvals. Ask the strata manager.
Should contingency be spent on upgrades?
Not without proper approval and a clear view of remaining repair risk.