Most room defects are easy to see before the wall lining goes on and difficult to find afterwards. This checklist is in the order the work normally happens.
Before the room closes
- Room type measured, including what differs from the drawings.
- Sample openings made and hazardous materials checked.
- Materials for the complete room ordered and confirmed.
- Water, power and data isolation points located.
- Adjoining rooms and corridors protected.
After strip-out
- Floors and walls checked for level, damp and damage.
- Corroded steel or cracked concrete reported.
- Old pipes, valves and drains assessed.
- Penetrations through fire-rated walls and floors recorded.
- Photos stored against the room number.
Before closing walls
- Plumbing pressure tested.
- Fixings for grab rails, televisions and joinery in place.
- Fire stopping installed and labelled.
- Insulation and acoustic details complete.
- Required inspections finished.
Bathroom
- Falls to the waste confirmed.
- Membrane applied to the specified areas and cured.
- Upstands and door junctions inspected.
- Flood or other specified testing recorded.
Finishes and handover
- Doors, locks, smoke seals and closers checked.
- Lighting, air conditioning and hot water commissioned.
- Silicone and movement joints complete.
- Defects photographed, closed and checked again.
- Room released in writing to the operations team.
Use a hold point
Nobody closes a wall until the "before closing walls" list is signed. That single rule prevents a large share of rework.
Read bathroom programs, soundproofing and fire stopping.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Who should sign the checklist?
The builder signs their stages, with inspections by whoever the contract or approval requires.
Should every room be photographed?
Yes. Photos by room number make later leaks and warranty questions much easier.
Can housekeeping inspect rooms?
They are excellent at finding finish and use problems, but hidden work needs technical inspection.