A hotel may have hundreds of near-identical bathrooms, but the pipes, slabs and walls behind them rarely match perfectly. A program works when it plans for repetition and expects differences.
Why stage by riser
Bathrooms stacked above each other commonly share water, drainage and exhaust. If valves do not isolate a single room, work in one can shut several. Closing a whole stack lets the team replace old pipes and valves together.
Investigate three things
- Can the water be isolated, and do the valves actually hold?
- What is the floor made of, and where does it fall?
- Are there pipes or cables where new fixings will go?
Prefabricated or built in place
Pods can reduce trades on site, but an existing building must have a route to bring them in and enough height. Wall panels reduce tiling time but still depend on a sound membrane and good joints. Traditional tiling adapts well to uneven rooms.
Protect waterproofing time
Drying and curing are steps, not spare time. Publish the earliest time the next trade may enter, and record the room temperature and product used. Walking on a fresh membrane can undo the whole room.
Test before tiles
Use the testing specified for the system and record it by room. If several rooms fail the same way, stop and change the detail before continuing.
Plan noise
Concentrate tile removal into agreed windows and leave empty rooms as a buffer above, below and beside the work.
Keep spares
Store matching tiles, trims and valve parts for later repairs.
Read bathroom leaks, accessible rooms and waterproofing.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
How long does one hotel bathroom take?
It depends on scope and product curing. A completed sample room gives the best local answer.
Can guests stay next door?
Sometimes, with a buffer and limited noisy hours. Demolition is usually the hardest stage.
Can new tiles go over old?
It may suit some sound surfaces, but falls, height, weight and unknown waterproofing must be checked.