On a large project, small delays in decisions become expensive. A scaffold may sit idle while owners argue over a detail that needed approval two months earlier.
Assign real roles
Write down who represents the owners, administers the contract, inspects work, approves money and speaks to residents. The strata manager, engineer and project manager have different jobs. Do not assume one person covers all three.
Set approval limits
Committees need a process for small changes, urgent safety work and large additions. State the evidence required: location, cause, quantity, price and program effect. Check that delegated authority fits strata rules.
Use one monthly page
- Work completed and next four weeks.
- Original budget, approved changes and forecast final cost.
- Open decisions and their deadline.
- Safety, complaints and quality issues.
- Photos of work about to be covered.
One clear page is more useful than fifty pages nobody reads.
Manage conflicts early
Committee members may be affected owners, investors or connected to a bidder. Record and manage interests before decisions. Independent contract administration can also protect trust.
Plan money before stages begin
Match levies, loans and progress claims to the program. Keep an honest contingency for hidden damage, and tell owners when it is being spent. Optimistic forecasts cause more anger later.
Close out properly
Final payment should not depend on memory. Use a checklist of defects, test results, warranties and drawings. See progress reports, contingency and strata works.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Do we need a project manager?
It depends on complexity and who is already responsible for contract administration.
Can the committee approve every variation?
Its authority depends on law, resolutions and limits. Ask the strata manager or lawyer.
How often should owners hear news?
Regularly, and before any change to access or cost reaches them by surprise.