Remedial works happen all year, but timing affects how smoothly they run. Weather, approvals, the strata meeting calendar and residents' plans all play a part.
Weather
Membranes, sealants and coatings need dry surfaces and suitable temperatures. Sydney's wet periods can stop waterproofing for days at a time, and summer storms can arrive with little warning. Extreme heat also shortens working time for some products and makes conditions hard for workers on roofs and scaffold.
That does not mean waiting for perfect weather. It means planning the program with weather days, sequencing roof and balcony work for the drier stretches where possible, and keeping temporary protection ready.
Work back from the start date
Most delays happen before work starts. A typical lead-in includes:
- Investigation and engineer's report.
- Regulated design and specification where the DBP Act applies.
- Tender, comparison and recommendation.
- General meeting approval and levy decision.
- Contract, permits and scaffold booking.
That can take months. If the committee wants work to start in a particular season, the investigation needs to start well before it. See how long strata remedial works take.
The AGM calendar
Many decisions, such as special levies, are made at general meetings. Missing an AGM can delay a project unless an extraordinary meeting is called. Read remedial works AGM motions.
Holidays and residents
Christmas and January are popular times for residents to travel, which can make access to units easier. They are also times when suppliers and some trades shut down. School holidays can mean more people home during the day. Ask residents about major events, such as weddings or births, that affect their units.
Do not wait on safety
If concrete is falling, a balustrade is loose or water is entering electrical areas, make it safe now regardless of season. See strata emergency leak response.
Talk to us about planning your strata remedial works.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can waterproofing be done in winter?
Yes, with the right products and dry conditions. Cold, damp days slow curing, so programs allow for it.
Does rain stop all remedial work?
No. Concrete repairs under cover and internal work can often continue.
How far ahead should we plan?
Start investigation months before you want work to begin, especially for regulated Class 2 work.