"How long will it take?" is one of the first questions owners ask. The honest answer depends on the size of the building, the work and how quickly decisions are made. Here is a realistic picture.
The stages
| Stage | What happens | Typical time |
|---|---|---|
| Investigation | Inspection, testing and report | A few weeks |
| Scope and quotes | Specification and tendering | Several weeks to a few months |
| Approval and funding | Meeting, levies and contract | Weeks to months, depending on meetings |
| Mobilisation | Permits, scaffold and notices | A few weeks |
| Works | Repairs on site | Weeks for small jobs, months for larger projects |
| Handover | Final inspections and records | A few weeks |
These are general guides only. Every building is different.

Typical work durations
- A few balconies: often a few weeks of site work.
- All balconies on a walk-up: often a couple of months.
- Whole facade and balcony program on a mid-rise: often many months.
- Large towers: can run a year or more, often staged.
What slows projects down
- Delayed decisions and meetings.
- Hidden damage that needs engineering advice.
- Access to apartments. See access to apartments.
- Wet weather, particularly for membranes and coatings.
- Permits and approvals. See scaffold permits.
- Material lead times, such as balustrades or special tiles.
How to keep works on track
- Approve a contingency and variation limits upfront. See AGM motions.
- Get access organised early with residents.
- Choose a builder with a realistic program, not just a fast one.
- Stage works so residents are affected for shorter periods.
- Keep communication regular. See progress reports.
How a well-run program helps owners
Shorter disruption, lower scaffold costs and a building that gets back to normal faster.
Get a realistic program
We include a program with our quotes, so committees know what to expect. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 work. Call 0415 840 500 or book a free inspection.
Frequently asked questions
How long do balcony repairs take in an apartment building?
A single balcony may take a couple of weeks of site work. A whole building program can take months, depending on size and access.
Why do strata remedial projects take so long to start?
Investigation, quotes, meetings and funding take time. Approving a clear scope and contingency upfront helps.
Can remedial works be done in winter?
Yes, though rain can delay membranes and coatings. Programs usually allow for weather.