An office floor can have a small core of shared toilets and hundreds of square metres without plumbing. A hotel may need a bathroom near every room. That single change affects slabs, ceilings, shafts and money.
Start with room depth
Guest rooms need a sensible relationship to windows. A deep floor may leave dark space in the centre that suits storage or services but not bedrooms. Test several room layouts before paying for full design.
Find the wet stack
Each bathroom must drain and ventilate. Long drainage runs need fall, which can use up ceiling height. Stacking wet areas and locating new risers early keeps more rooms workable.
Openings need structure
Stairs, lifts and risers may cross beams, reinforcement or post-tension. Scanning and engineering should guide positions. A beautiful plan with an impossible shaft is not a concept worth pricing.
Think about sound
Office partitions may stop above a ceiling or share light framing. Guest rooms need better sound and fire separation through walls, floors, doors and service gaps.
Upgrade the building once
Check facade leaks, roof plant, lifts and concrete before work begins. If bathrooms come in on every floor, finding a failed facade after tiling is expensive.
Construction stages
- Survey, scan and investigate.
- Build one room and one riser prototype.
- Create new shafts and structural openings.
- Install main services and weatherproofing.
- Complete rooms by stack.
- Commission and hand over in safe zones.
Read slab openings, change of use and structural upgrades.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Are office buildings easier than new hotels?
They can save structure, but services, floor depth and approvals may be difficult.
Can old offices carry bathrooms?
Often with suitable design. The engineer must check screeds, tiles, walls and equipment.
Can we keep tenants on other floors?
Sometimes. Noise, services, access and fire staging decide.