Doing every building at once can overwhelm parking, access and the repair team. Doing them randomly can miss safety problems and leave owners feeling treated unfairly.
Rank risk, not noise
Score safety, water entry, structural condition and rate of deterioration. The building with the loudest complaints is not always the one at greatest risk. Publish the method so owners can see why the order was chosen.
Start with a pilot
Choose one representative block and test the investigation, repair details, resident notices and measured quantities. Review it before the next stage. Changing a poor detail after one block is cheaper than after six.
Stage around shared systems
Check whether buildings share a podium, basement, drainage, power or fire exits. A boundary between building names may mean little to the structure below.
Build a fair access plan
- Share loss of parking where practical.
- Give longer notice for long balcony closures.
- Coordinate removals, school access and waste collection.
- Keep accessible paths and emergency routes open.
Use quantities with care
Similar blocks may have different weather exposure and past repairs. Apply pilot quantities as a forecast, then update them after close inspection.
Contract choices
A framework can lock rates and quality requirements while letting each stage be approved separately. Include price adjustment, exit points and who holds site records.
Read building-wide balcony programs, prioritising repairs and strata remedial.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Must all buildings use one builder?
Not necessarily. Compare continuity against competition, warranties and shared site responsibility.
Should each block pay separately?
Cost allocation depends on the scheme and by-laws. Obtain strata advice.
Can works stop after the pilot?
Only if the contract and staged approvals allow it. Set that out before signing.