Floors, roofs and cross walls often brace a facade. Remove them and a wall that has stood for a century can become unstable. Facade retention provides new temporary support until the permanent building can take over.
Understand the old wall
Survey lean, cracks, openings, bond and footings. Investigate parapets, lintels and stone fixings. Drawings may not show past alterations, so controlled openings can be important.
Choosing the support
Steel frames may be inside, outside or both. They can use concrete ballast or ground anchors. Footpaths, trees, services and future excavation affect which layout works.
Sequence matters
- Record condition and set monitoring points.
- Build temporary foundations and frame.
- Connect the facade as designed.
- Remove floors in the stated sequence.
- Build permanent structure and connect it.
- Transfer load and remove support last.
Watch the base
Excavating beside the footing can undo the work above. The facade may need underpinning or a piled support before the dig. Vibration also needs consideration.
Approval and price risks
Heritage conditions, traffic space, crane access and unknown masonry can affect time. Tenderers should price the same temporary works scope. "Facade support by builder" is too vague for a complex wall.
Questions for the team
Who designs each stage? What movement is allowed? Who can stop work? What happens if the old wall differs from the drawings? Agree answers before demolition begins.
Related: heritage restoration and underpinning.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can scaffold hold a facade?
Ordinary access scaffold should not be assumed to do so. Retention needs engineered support.
How is movement checked?
Surveys, tilt and crack monitoring may be used with agreed action limits.
Is facade retention always heritage work?
Often, but a wall may also be kept for planning or boundary reasons.