Owners may report hundreds of items after handover. The builder needs a method that separates one-off defects from repeated design or construction issues.
Build the register properly
For every item record location, symptom, photo, priority, suspected cause, access, repair and proof. Merging duplicates can hide that one detail failed in forty units, so link repeat items to one cause while retaining each location.
Find the cause before repairing
A wall patch may conceal a leaking membrane. A new window seal may not fix missing flashing. Open representative areas and agree a trial detail before scaling it.
Check registration and scope
Class 2 work may need registered practitioners and declared designs. Confirm the applicable scheme, insurance and who is the responsible head contractor. Do not rely only on a trade licence.
Plan resident access
Publish work, entry and reinstatement dates. Provide a named contact who can answer whether a defect is accepted, inspected, repaired or closed.
Measure completion honestly
- Agreed repair method.
- Required inspection passed.
- Photos of hidden stages.
- Owner notified and finishes reinstated.
- Any warranty or maintenance record issued.
An empty register because people stopped responding is not completion.
Financial control
Track original responsibility, extra uncovered work and upgrades separately. It is easier to settle an insurer, developer or contractor dispute with that record.
See developer complaints, Class 2 builder and building defect rectification.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can the original builder rectify?
Possibly, but contract, trust, access and technical independence should be considered.
Who verifies Class 2 repairs?
The relevant design and building practitioners, engineer and approval pathway set requirements.
Are all defects urgent?
No. Set safety and water-entry priorities with an agreed register.