Facade work can occupy every room on one elevation, not just the room being repaired. Scaffold, noise and closed windows make it an operating project as much as a construction one.
Inspect before access is ordered
Use drawings, close samples and suitable lifting or rope access to understand concrete, joints, brick, windows and balconies. If defects cross several levels, choose access that allows every trade to work.
Work in vertical zones
Closing one vertical strip can reduce how often scaffold moves and keep the remaining rooms available. Balcony and window trades should finish in that zone before access leaves.
Protect guest privacy
- Lock or close balconies as directed.
- Provide screens and secure access after hours.
- Warn guests before workers appear at windows.
- Keep room lights and alarms working.
- Assign a contact at reception.
Separate noise by floor
Concrete breaking may affect levels well away from the crew. Build buffer rooms into the booking plan instead of only blocking the room with the defect.
Finish the water path
Repair cracks, joints, window perimeters and balcony edges before coatings. New paint should not hide one unfinished joint between trades.
Inspect before the scaffold moves
Photograph each bay, complete the defect list and get required approval. Returning for a missed window seal may cost more than the seal itself.
Plan signs and lights
Corroded fixings can be repaired while access is available, but owner approvals and electrical isolation need to be in the program.
See facade project stages, hotel balconies and facade repairs.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can guests use their balcony?
Not where access, repair or overhead work makes it unsafe. Lock and sign closed areas.
Can facade work happen only from outside?
Many repairs can, but windows, concrete and drainage may need internal access.
Can noisy work be limited to check-out hours?
It can help, but approvals and safe concrete work may require longer periods.