Replacing a leaking sliding door without checking the balcony membrane can move the same leak into a new frame. A whole-building program should treat the opening and balcony as one system.
Measure each opening
Openings may look identical on drawings and differ on site after settlement or past repairs. Check levels, waterproofing upstand, drainage, internal floor and balustrade before ordering doors.
Decide the access height
An old threshold may be hard for some residents to cross. Lowering it can affect the membrane, drainage and compliance, so design the compromise rather than choosing a door catalogue size.
Common combined work
- New door and frame.
- Waterproofing upstand repairs.
- Balcony falls and drain.
- Internal flooring and painting.
- Security, screens and access hardware.
Owners should agree which finishes are like-for-like and which are upgrades.
Pilot one opening
A trial reveals frame fixings, membrane transition, glazing tolerance and resident access. Keep it open to inspection before ordering the rest.
Stage the building
Group stacks or floors with the same scaffold and protect each room on the same day doors are removed. Temporary security and weather protection must be ready before a frame comes out.
Handover
Test water, drainage, locks and slip-resistant finishes. Record every serial number and maintenance detail. See sliding door leaks, door threshold step-down and balcony repairs.
Call 0415 840 500 or book an inspection. METCON is a licensed NSW builder (384697C) and DBP registered (BUP4254812).
Frequently asked questions
Can the same door suit every balcony?
Not unless measured openings, structure and waterproofing details match.
Must balconies be waterproofed too?
Not always, but the door-to-membrane junction must be resolved.
Can residents sleep there that night?
Only with a secure, weather-tight opening and agreed completion sequence.