Before Your Strata Warranty Ends: Defect Checklist

18 November 2026 · 4 min read · By the METCON team

Newer apartment buildings in NSW are covered by statutory warranties under the Home Building Act 1989. Once those periods end, claims against the builder or developer become much harder. Many owners corporations only realise this after the date has passed.

The two dates that matter

Defect typeWarranty periodWhen to start the inspection
Other defects2 years from completionAround 18 months after completion
Major defects6 years from completionAt least 6 to 12 months before the end

Confirm the completion date and how the time limits apply to your building with your lawyer.

What to inspect

  • Balconies: leaks, falls, drainage, door sills, balustrades. See new apartment balcony defects.
  • Roofs and podiums: membranes, outlets, overflows, planters.
  • Facade: cracking, sealants, window leaks, cladding fixings.
  • Basement and carpark: water entry, cracking, drainage, pumps.
  • Wet areas: leaks into units below.
  • Fire safety: fire doors, penetrations and separation.
  • Structure: cracking in slabs, walls and transfer elements.

Ask the residents

Send a short survey to every owner and tenant asking about leaks, cracks, damp and doors or windows that stick. Residents see things inspectors miss.

Turn it into evidence

  1. A building-wide defect report, by location.
  2. Cause, scope and cost for each defect.
  3. Formal notice to the builder and developer.
  4. Legal advice on protecting the claim before the deadline.

See claiming against the developer.

The building bond scheme

Eligible buildings also go through interim and final inspections under the strata building bond scheme. That process has its own timing and does not replace warranty claims. See the building bond scheme.

Strata defect reports in Sydney

We prepare building-wide defect reports with itemised rectification costs. See strata defect reports. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book a free inspection.

Frequently asked questions

When does the warranty period start?

Generally from completion of the work. For strata buildings, completion is often linked to the occupation certificate. Confirm with your lawyer.

Is a waterproofing failure a major defect?

It can be, if it causes or is likely to cause the building to be uninhabitable or seriously damaged. Each case depends on the facts.

Can we claim after the warranty ends?

Possibly under other routes, such as the DBP Act duty of care, which has a longer period. Get legal advice.

Written by the METCON teamMeteora Constructions Pty Ltd. Licensed NSW builder 384697C, DBP registered BUP4254812, 40+ years building across Sydney.
Related services

How we can help.

Everything in this article is work we do every week across Sydney.

Strata Remedial Works
Keep reading

More articles.

Practical guides from a licensed Sydney builder.

All articles

Got a project in mind?

Book a free site assessment. Straight answers on cost, scope and timeline.

Call now Free Quote