Many Sydney apartment buildings sit close to the boundary. To repair a side wall, replace windows or fix a roof edge, the scaffold may need to go on the neighbour's land. That needs the neighbour's agreement, or a court order.
Start with an agreement
Most neighbours agree when approached early and treated fairly. A written access agreement should cover:
- The area to be used and for how long.
- Access hours and who can enter.
- Protection of gardens, fences, paving and windows.
- Insurance, and who pays for any damage.
- Any fee or compensation for the use of the land.
- Restoration at the end.
Record the condition first
A dilapidation report on the neighbour's property before work starts protects both sides. It records existing cracks and damage, so new damage can be identified and fixed fairly. See dilapidation reports.
If the neighbour says no
NSW has a law for this: the Access to Neighbouring Land Act 2000. In summary, an owner who needs access to adjoining land to carry out certain work on their own land can apply to the Local Court for an access order, if the neighbour will not agree. The court can set conditions, including compensation and protection of the neighbour's property. Get legal advice before applying.
Alternatives to scaffold on their land
- Swing stages or rope access from the roof.
- Cantilevered scaffold supported from the building itself.
- Elevated work platforms from your own land, where there is room.
Council and public land
Scaffold or hoarding over a footpath or road needs council approval. See scaffold and hoarding permits.
Planning access
We plan access for remedial works on tight sites, including neighbour agreements and condition reports. See strata remedial works and dilapidation reports. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book an inspection.
Frequently asked questions
Can we put scaffold on the neighbour's land without asking?
No. You need their agreement or a court order.
Do we have to pay the neighbour?
Often a fee or compensation is agreed. Under a court order, the court can decide compensation.
How long does a court access order take?
It varies. Approach the neighbour early so the works program is not delayed.