NCAT Procedural Direction 3 (PD3) sets out how expert evidence must be prepared and presented at the Tribunal. The current version took effect on 7 April 2025 and is read together with Procedural Direction 7 on the use of generative AI. If you are in a building dispute, it affects you.
When it applies
- Proceedings where the rules of evidence apply.
- Home Building Act claims in the Consumer and Commercial Division where the amount claimed or in dispute is more than $30,000.
- Certain Occupational Division matters.
- Any other proceedings where the Tribunal directs it.
Duties of the person hiring the expert
If you engage an expert for a matter covered by PD3, you must bring PD3 and its code of conduct to the expert's attention, including the parts of PD7 that deal with expert reports.
The experts' code of conduct
- An expert has an overriding duty to help the Tribunal impartially.
- Their paramount duty is to the Tribunal, not to the party paying them.
- An expert is not an advocate.
- When directed to confer with other experts, they must use independent judgment, try to reach agreement and not follow any instruction to avoid agreement.
What a report must contain
| Requirement | In plain English |
|---|---|
| Code acknowledgement | The expert has read the code and agrees to be bound |
| Qualifications | Who they are and why they are qualified on this issue |
| Relationships | Any link to the party and any conflict of interest |
| Instructions | What they were asked and what documents they had |
| Facts and assumptions | What the opinions are based on |
| Reasons | Why they hold each opinion |
| Limits | Anything outside their expertise, or not a concluded opinion |
| Declaration | All appropriate inquiries made, nothing significant withheld |
| Summary | For long or complex reports |
Extra rules for building work
Where a report deals with completing or rectifying residential building work, or an owners corporation's duty to repair under the Strata Schemes Management Act 2015, it must also include the reasons for any recommended rectification, the scope of the works, the likely costs and how they were calculated, and whether there is a reasonable alternative remedy.
This is why a costed scope matters. See builder's quotes for NCAT.
What if a report does not comply?
Where the rules of evidence apply, a non-compliant report may be inadmissible. In other matters, it is still admissible but may be given less weight. Either way, it weakens your case.
Conclaves and joint reports
Experts must follow directions to attend a conclave, try to agree, prepare a joint report and give evidence together. See conclaves and joint reports.
Reports written to PD3
Our NCAT reports follow PD3 and include itemised, fixed-price rectification costs. See NCAT expert reports. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Does PD3 apply to claims under $30,000?
Not automatically for home building claims, but the Tribunal can direct that it applies. Following it anyway makes your evidence stronger.
Can an expert use AI to write a report?
Procedural Direction 7 restricts and requires disclosure of generative AI use in expert reports. Check the current direction and ask your expert how they prepare reports.
Does the expert have to sign the report?
It is good practice to sign and date it. Follow any specific direction from the Tribunal.