Builder Licence 384697C DBP BUP4254812 Demolition AD214430
7 days, 7am to 7pm 0415 840 500
Strata

The Defects Liability Period on Strata Remedial Contracts

23 November 2026 · 4 min read · By the METCON team

When a remedial project reaches practical completion, the owners corporation gets the building back. But the contract does not end there. Most remedial contracts include a defects liability period, during which the builder must return to fix defects that appear.

What it is

The defects liability period is a contractual period, often 6 or 12 months from practical completion, set out in the contract. During it, the builder must fix defects in their work when notified. It sits alongside, and does not replace, the statutory warranties under the Home Building Act for residential building work.

How it works in practice

  • Owners report issues to the strata manager or superintendent, not directly to workers on other sites.
  • The builder is notified in writing and given access to inspect and repair.
  • Repairs are done within a reasonable time, or as the contract sets out.
  • At the end of the period, a final inspection is held.

Retention

Many contracts hold back a small percentage of the contract price, or a bank guarantee, as security until the end of the defects liability period. Once defects are fixed, it is released. See retention and security.

Use the period well

  • Ask residents to report leaks and issues promptly.
  • Check balconies and roofs after the first big storms.
  • Do a walk-through a month or two before the period ends.
  • Keep photos and dates of anything reported.

What is not a defect

Damage caused by residents, lack of maintenance such as blocked drains, or work done by others is not usually the builder's responsibility. Clear handover instructions help everyone. See practical completion and handover.

We stand behind our work

We return promptly to inspect and fix any issue in our work during the defects liability period, and beyond. See strata remedial works. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book an inspection.

This article is general information, not legal advice. Check current requirements with NSW Fair Trading, the Building Commission or a strata lawyer.

Frequently asked questions

How long is a defects liability period?

It is set by the contract, often 6 or 12 months from practical completion.

Does the warranty end with the defects liability period?

No. Statutory warranties under the Home Building Act run separately and for longer.

Who reports defects to the builder?

Usually the strata manager or the superintendent, in writing, so there is a record.

Written by the METCON teamMeteora Constructions Pty Ltd. Licensed NSW builder 384697C, DBP registered BUP4254812, 40+ years building across Sydney.
Related services

How we can help.

Everything in this article is work we do every week across Sydney.

Strata Remedial Works
Keep reading

More articles.

Practical guides from a licensed Sydney builder.

All articles

Got a project in mind?

Book a free site assessment. Straight answers on cost, scope and timeline.

Call now Free Quote