A Scott Schedule is a table that lists each item of defective or incomplete work in a building dispute, along with what each side says about it. NCAT describes it as a form that lets parties itemise the defective and incomplete works in a home building dispute. It is generally used in complex matters or where there are many defects.
When does NCAT direct one?
At a directions hearing, the Tribunal can make directions for the parties to file evidence, including expert reports, a Scott Schedule and a bundle of documents. If your matter has lots of defects, expect one.

A typical layout
| Column | What goes in it |
|---|---|
| Item number | A number used across every document |
| Location | Exactly where the defect is |
| Description | What is wrong |
| Why it is defective | The plan, contract term, code clause or standard it fails |
| Rectification | What is needed to fix it |
| Owner's cost | The cost of rectification claimed |
| Builder's response | Agreed, disputed and why, and their cost |
| Tribunal column | Left blank for the member's decision |
Always use the format the Tribunal or your lawyer gives you.
Common mistakes
- Vague descriptions like "poor workmanship throughout".
- No costs, or one total at the bottom.
- Inconsistent numbering between the expert report and the schedule.
- Double counting shared costs like scaffolding in every item.
- Including things that are not defects, which damages credibility.
How shared costs are handled
Scaffolding, site setup and supervision often cover many items. They are usually shown as a separate line or spread across items in a stated way, so they are counted once.
Responding to a Scott Schedule
If the other side has served one, respond to every item: agreed, agreed in part or disputed, with reasons and your own costing. Silence can be treated as agreement.
How it helps
A clear schedule lets experts agree more items at a conclave and lets the member decide item by item. That usually means a shorter hearing. See expert conclaves.
Scott Schedules in Sydney
We prepare and cost Scott Schedules as builders who price this work every week. See Scott Schedules. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Who prepares the Scott Schedule?
Usually the applicant, often with their expert, and the respondent then adds their responses. The Tribunal's directions will say who does what and by when.
Does a Scott Schedule need costs?
It should. Without costs, the Tribunal cannot work out what to award for each item.
Why is it called a Scott Schedule?
It is named after an official referee in the English courts who popularised the format. The name stuck.