What Is a Scott Schedule? NCAT Building Disputes

18 November 2026 · 4 min read · By the METCON team

A Scott Schedule is a table that lists each item of defective or incomplete work in a building dispute, along with what each side says about it. NCAT describes it as a form that lets parties itemise the defective and incomplete works in a home building dispute. It is generally used in complex matters or where there are many defects.

When does NCAT direct one?

At a directions hearing, the Tribunal can make directions for the parties to file evidence, including expert reports, a Scott Schedule and a bundle of documents. If your matter has lots of defects, expect one.

A defect opened up so its extent can be scoped and costed.
A defect opened up so its extent can be scoped and costed.

A typical layout

ColumnWhat goes in it
Item numberA number used across every document
LocationExactly where the defect is
DescriptionWhat is wrong
Why it is defectiveThe plan, contract term, code clause or standard it fails
RectificationWhat is needed to fix it
Owner's costThe cost of rectification claimed
Builder's responseAgreed, disputed and why, and their cost
Tribunal columnLeft blank for the member's decision

Always use the format the Tribunal or your lawyer gives you.

Common mistakes

  • Vague descriptions like "poor workmanship throughout".
  • No costs, or one total at the bottom.
  • Inconsistent numbering between the expert report and the schedule.
  • Double counting shared costs like scaffolding in every item.
  • Including things that are not defects, which damages credibility.

How shared costs are handled

Scaffolding, site setup and supervision often cover many items. They are usually shown as a separate line or spread across items in a stated way, so they are counted once.

Responding to a Scott Schedule

If the other side has served one, respond to every item: agreed, agreed in part or disputed, with reasons and your own costing. Silence can be treated as agreement.

How it helps

A clear schedule lets experts agree more items at a conclave and lets the member decide item by item. That usually means a shorter hearing. See expert conclaves.

Scott Schedules in Sydney

We prepare and cost Scott Schedules as builders who price this work every week. See Scott Schedules. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee before we start.

This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.

Frequently asked questions

Who prepares the Scott Schedule?

Usually the applicant, often with their expert, and the respondent then adds their responses. The Tribunal's directions will say who does what and by when.

Does a Scott Schedule need costs?

It should. Without costs, the Tribunal cannot work out what to award for each item.

Why is it called a Scott Schedule?

It is named after an official referee in the English courts who popularised the format. The name stuck.

Written by the METCON teamMeteora Constructions Pty Ltd. Licensed NSW builder 384697C, DBP registered BUP4254812, 40+ years building across Sydney.
Related services

How we can help.

Everything in this article is work we do every week across Sydney.

Inspections & Reports
Keep reading

More articles.

Practical guides from a licensed Sydney builder.

All articles

Need a report for NCAT, court or insurance?

Fixed fee agreed before we start. Clear findings, an itemised scope and a fixed-price rectification quote.

Call now Request Report