On a large remedial project, someone has to check progress claims, approve variations, inspect hold points and keep the committee informed. Strata managers are rarely set up to do all of that. That is where a superintendent or project manager comes in.
What a superintendent does
In Australian Standard contracts like AS 4000, the superintendent administers the contract on the owner's behalf and must act honestly and fairly in certain roles.
- Assesses and certifies progress claims.
- Assesses and directs variations.
- Assesses extensions of time.
- Issues instructions to the builder.
- Certifies practical completion.
Who usually fills the role
| Who | Strengths |
|---|---|
| Remedial engineer | Wrote the specification, inspects hold points |
| Project manager | Contract, cost and program management |
| Building consultant | Practical building knowledge |
When it is worth it
- Building-wide programs such as all balconies or the whole facade.
- Large budgets funded by special levies or loans.
- Regulated work under the DBP Act with multiple designers.
- Committees with limited time or building experience.
When it may not be needed
A smaller, well-defined job, such as one balcony to an engineer's specification, can often be run directly between the strata manager, engineer and builder, with the engineer inspecting hold points.
Who does what
Whatever the structure, write down who approves variations, who signs off quantities, who talks to residents and who reports to the committee. Confusion over roles causes most remedial disputes. See strata and building manager roles.
Working with your team
We work with superintendents, engineers and project managers on strata remedial projects, with clear records for every claim and variation. METCON is a licensed builder (384697C) and DBP registered (BUP4254812) for Class 2 apartment buildings. Call 0415 840 500 or book a free inspection.
Frequently asked questions
Can the strata manager be the superintendent?
It is possible on small jobs, but most strata managers do not have the building knowledge or time for large remedial projects.
Who pays the superintendent?
The owners corporation. The fee is usually part of the project budget.
Is the superintendent on the owners' side?
They act for the owner, but in certain roles, such as certifying payments, they must act honestly and fairly.