Good expert evidence starts with a good brief. This guide is for solicitors instructing a building expert in a NSW defect, cost or contract dispute, whether at NCAT or in court. It sets out what helps the expert give you a report that is useful, compliant and on time.
1. Make first contact early
Call before directions are made if you can. The expert can tell you whether the issues are in their field, whether testing or opening up is needed, and how long it will take. That helps you propose a realistic timetable.
2. The letter of instruction
- The parties, the property and the forum.
- The relevant directions and dates.
- The applicable rules: NCAT Procedural Direction 3, or UCPR Part 31 and the Schedule 7 code.
- Specific questions, numbered.
- Assumptions the expert should make, stated separately.
- The documents provided, listed.
3. Good questions
- Is each item in the schedule defective? If so, why, by reference to the contract, plans, NCC and standards?
- What is the cause of each defect?
- Is each item a major defect within s 18E of the Home Building Act?
- What is the appropriate method of rectification?
- What is the reasonable cost of that rectification, itemised?
- Is there a reasonable alternative method, and its cost?
4. Documents
Contract and special conditions, approved plans and specifications, engineering, certificates, variations, payment records, correspondence, photos, the Fair Trading file, the opposing party's evidence and any previous reports. A chronological index saves time and fees.
5. Access and testing
Arrange access early. If testing or destructive investigation is needed, agree it with the other side or seek directions. Reports that rely on testing are more persuasive.
6. Costing
Decide whether you need a cost estimate or a fixed-price quote. A builder who prices the work as they would build it, at a fixed figure, gives you costing that is difficult to attack.
7. Conclaves and joint reports
Tell the expert about likely conclaves. Remember the expert must not be instructed to withhold agreement. See conclaves and joint reports.
8. Fees
We agree a fixed fee for each stage in writing before work starts: inspection and report, reply report, conclave and attendance. No open-ended hourly billing.
About us
METCON is a Sydney remedial builder. We rectify the kinds of defects we report on. See court expert witness and NCAT expert reports. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee in writing before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Can you provide a CV and sample report?
Yes. We can provide qualifications and experience, and a redacted sample, before you instruct us.
Do you do quantum only?
Yes. We can cost another expert's scope, or cost the competing scopes of both experts, as a fixed-fee brief.
Can you attend a site meeting before the report?
Yes. An early site meeting with the client or other experts is often worthwhile, and we price it in the fixed fee.