In a building defect claim, winning on the defect is only half the job. The other half is proving what it will cost to fix. Tribunals and courts deal with cost arguments all the time, and the evidence that holds up has a few things in common.
The basic rule
Australian law has long held that an owner is generally entitled to the cost of making the work conform to the contract, so long as the rectification is necessary to achieve that and is a reasonable course to adopt. The well-known High Court case is Bellgrove v Eldridge. In plain terms: you get the cost of a reasonable fix, not the cost of gold-plating, and not a token amount if the reasonable fix is a full rebuild.

What makes costs credible
- A defined scope. The cost follows a written scope of what has to be done, item by item.
- Itemised pricing. Labour, materials, plant, access, waste and preliminaries shown separately or clearly built in.
- Market rates. Prices a licensed builder would actually charge to do the work in Sydney now.
- The right sequence. Removal, making good, and the other trades affected, such as tiling after waterproofing.
- Allowances explained. Contingencies, provisional sums and margins stated and justified.
Common arguments from the other side
| Argument | How good evidence answers it |
|---|---|
| "A patch would do" | Explains why a patch will not stop the defect returning. |
| "That is betterment" | Shows the scope only restores what the contract required. |
| "The rates are too high" | Breaks rates down and shows they are market. |
| "You are double counting" | Each item has its own scope and no overlap. |
| "The original builder could do it cheaper" | Explains the cost of another builder taking over defective work. |
Estimate or fixed price?
A cost estimate is an opinion. A fixed-price quote from a licensed builder ready to do the work is a market fact. Both can be evidence, but a fixed price is harder to attack. See fixed price vs estimate.
Consequential costs
Depending on the case, claims may also include things like alternative accommodation while the work is done, storage and repairs to finishes damaged by the defect. Your lawyer will advise what can be claimed.
Fixed-price rectification costing
We price rectification the way we would build it. See fixed-price rectification quotes, and Scott Schedules where costs are compared item by item. METCON is a licensed builder (384697C) and DBP registered (BUP4254812), and we fix building defects for a living. Call 0415 840 500 or request a report or quote. We confirm a fixed fee in writing before we start.
This article is general information, not legal advice. For your situation, speak to a lawyer, NSW Fair Trading or the Tribunal.
Frequently asked questions
Does the Tribunal always award the full quote?
No. It assesses each item on the evidence, and may allow some items in full, reduce others and reject some. Itemised costs let it do that without throwing out the whole figure.
Should I get three quotes?
More than one can help, but one well-scoped, itemised fixed-price quote with an explanation is often better evidence than three lump sums.
Can I claim the cost of the expert report?
Costs rules at NCAT and in the courts are different and depend on the claim. Ask your lawyer.